Weekly Update and Two-week Projection of Work from Roy F. Weston, Inc.

December 8, 2000

 

Anne Piekarski of Roy F. Weston, Inc. (www.rfweston.com) sent the following information to The Cattail Press. Weston is the primary contractor working on the Eastland Woolen Mill Site in Corinna. My thanks to Weston for providing this information.

 

PUBLIC WEEKLY UPDATE

NON-TIME CRITICAL REMOVAL ACTION

EASTLAND WOOLEN MILL SITE

CORINNA, ME

 

The following summarizes WESTON's work completed on the Eastland Woolen Mill Site for week ending Friday December 08, 2000:

 

Safety Update:

  • Conducted daily safety inspections on the heavy equipment used on site.
  • Conducted air monitoring in work areas (Odd Fellows foundation and bridge excavation area).
  • Workers around the work areas continued to wear level D personal protective equipment.

 

Work Accomplished by WESTON:

  • Subcontractor oversight.
  • Continued securing winter cover on contaminated soil stockpile.
  • Completed backfilling Building 9 UST excavation area.
  • Completed cleaning of one frac tank.
  • Began removing pumps and associated river diversion piping from the site.
  • Installed a warning sign at the southern end of the snowmobile trail that leads through the site.
  • Operated on-site water treatment plant.
  • Continued general clean-up and winterization of site.
  • Lowered Odd Fellows Building 6".
  • Continued constructing form-work for bridge abutments #1 and #2.
  • Completed an approximately 45yd3 pour on abutment #2.

 

Two-week Projection:

The following summarizes the anticipated work to be completed for the next two week time period (December 11 through December 26):

  • Continue ongoing maintenance of erosion controls, construction fencing, and security fence around the work site.
  • Continue bridge construction.
  • Complete lowering of Odd Fellows Building onto new foundation.
  • Pour Odd Fellows Building cellar floor.
  • Monitor winter cover on contaminated soil stockpile.

 


 